Bridge Construction & Repair

Construction of a Link Bridge Building at University Hospital. Cork City

Contract Details:

Cumnor Construction Ltd. carried out the role of Works Contractor and PSCS for this project.

The works were carried out under the GCCC Public Works Form of Contract for Minor Building and Civil Engineering Works designed by the Employer.

The contract involved the construction of a new link bridge corridor in two phases at first floor level. The work was carried out within a busy, active, live acute hospital and therefore a high level of care was necessary to ensure the safety of the patients, staff and members of the general public.

The building remained fully open and live directly below the works. Noise restrictions were in place as the works were being carried out directly above theatre rooms and patient rooms. There was a requirement for the installation of new specialised mechanical and electrical equipment.

Contract:

Construction of a New Link Bridge Building at Cork University Hospital, Cork City

Client: Health Service Executive (HSE)
Year: 

Fortress Spike Island. County Cork

Contract Details:

Cumnor Construction Ltd. carried out the role of Works Contractor and PSCS for this project.

The work comprised of the conservation and restoration of protected structures and a national monument. This included modern interventions and substantial Civil Engineering infrastructure work.

This contract involved the development of ten interlinked building and infrastructure projects which were developed on the island. These included various new buildings, conservation, restoration and repair work as well as civil infrastructural project work. Best practice conservation techniques were carried out on the site.

Contract:

Redevelopment of Fortress Spike Island as a Visitor Attraction.

Client: Cork County Council
Year: 

Convent Garden. Kinsale, County Cork

Contract Details

Cumnor Construction Ltd. carried out the role of Works Contractor and PSCS for this project.

The works involved the construction of twenty-one luxury houses in a mixture of two and three bedroom properties. The houses achieved A Energy rating.

External works included new foul and storm water systems, watermains and all services, construction of roads and paths and the installation of lighting.  There are substantial reinforced concrete retaining walls included in the siteworks also.

The works were carried out within Kinsale Town, a busy tourist destination. The roads within the town are narrow and often one-way traffic is allowed. Traffic management plans were therefore designed in order to co-ordinate deliveries to the site. This required having larger deliveries to the site during off peak times as roads were often required to close temporarily in order to facilitate the deliveries.

Noise, dust and vibration control measures were in place in order not to impact the neighbouring environment.

 

Contract:

Construction of a Residential Development at Convent of Mercy, Kinsale, County Cork.

Client: Blarney Properties
Year: 2011

Slope Stabilisation. Cobh, County Cork

Contract Details

Cumnor Construction Ltd. carried out the role of Works Contractor and PSCS for this project.

New reinforced concrete retaining walls were constructed in various locations throughout Cobh. These retaining walls were then clad with natural stone. Remedial work to other masonry walls was also carried out. This included removal of vegetation and existing deteriorated pointing. Repointing was carried out and sections of the retaining walls were rebuilt. Much of this work required netting and underpinning. Tie bars were drilled through the existing walls and grouted to further support these old masonry walls.

A new earth embankment was designed and constructed. This embankment was built directly behind existing houses. The work area was extremely restricted with special equipment required to carry out the project.

Soft and hard landscaping work was completed. Existing damaged footpaths were removed and replaced with new concrete reinforced footpaths. A new road drainage system was installed.

Detailed traffic management plans were implemented. All roads remained open while the work was being completed. Adequate signage and traffic controls were implemented in co-ordination with Cobh Town Council, Cork County Council and An Garda Síochána.

 

Contract:

Slope Landslide & Stabilisation. Cobh, County Cork

Client: Cobh Town Council
Year: 

National Rowing Centre. County Cork

Contract Details:

Cumnor Construction Ltd. carried out the role of Works Contractor and PSCS for this project.

This project comprised of the extension and refurbishment of the existing training facility. The work included extending the existing facility and the addition of another floor over the main footprint of the building. A viewing balcony was located at this level. Accommodation within the facility included gym, changing areas, toilets, meeting rooms, boat bays, foyer, offices, kitchen, and function room.

A protected access route on the existing road was provided to ensure that the facility could remain open to the public and operational throughout the contract.

Contract:

Extension and Refurbishment of National Rowing Warehouse and Community Resource Centre, Farran, County Cork

Client: National Rowing Union
Year: 

R.N.L.I Lifeboat Station. Youghal, County Cork

Contract Details:

Cumnor Construction Ltd. carried out the role of Works Contractor and PSCS for this project.

The works included the construction of a two-storey building. Construction was in blockwork with reinforced concrete, steel and timber structural elements.  External materials included natural stone cladding and rendered walls.

Internal accommodation included a large boathouse, changing rooms, showers, office and operations room. Mechanical and electrical works were carried out throughout the building. Site work including soft and hard landscaping.

Noise and Traffic management plans were prepared by Cumnor Construction Ltd. and approved by An Garda Síochána.